The Markley Group demonstrates how power at a UPS in a data center is transferred without its critical loads seeing any interruption. Routinely this type of procedure is performed at One Summer Street to allow technicians to safely work on critical electrical equipment without any risk to your information. Video by Christopher Huang

21 Comments

  1. Not Sure - 2020 on April 12, 2021 at 11:53 pm

    I recognized those units @0:16 , APC.

  2. swastik mishra on April 12, 2021 at 11:55 pm

    Very nice

  3. jejedala on April 12, 2021 at 11:56 pm

    hymm.. no ups power directly to critical it ??

  4. hotrex7 on April 12, 2021 at 11:57 pm

    Looking at your schematic drawing I would ask why do you put you it load at risk and run on generator raw power when you could isolate one ups system to work on and use the second ups system to power the load and maintain ups support to your it load . As a data Center I would expect you to have a minimum off N+1. So 1 ups should be able to take the load .
    This is something that I do as a regular switching operation for ups maintenance.

  5. Obviously on April 13, 2021 at 12:01 am

    I don’t even own a critical data centre but when I do, i’ll know what to do

  6. Dip H on April 13, 2021 at 12:09 am

    Space suit??

  7. MrVM77 on April 13, 2021 at 12:11 am

    As ups enginner this kind of job is very critical.
    The easiest way to fired you? Just cut of the load!!!

  8. Chia hung Lin on April 13, 2021 at 12:11 am

    This can use DRUPS to make thing easier, it is automatically transfer u power and normally transfer to gen set power within few seconds.

  9. Brian Dantonio on April 13, 2021 at 12:12 am

    That is some out of date equipment by today’s standards

  10. Zul Yadein on April 13, 2021 at 12:13 am

    youtube help full my job

  11. Ever Online on April 13, 2021 at 12:24 am

    Somebody should show this to the technicians from ovh….

  12. Boris Hab on April 13, 2021 at 12:36 am

    No arc flash label in sight !

  13. C. J. on April 13, 2021 at 12:37 am

    What kind of suit is that at 1:24?

  14. sjf 440 on April 13, 2021 at 12:38 am

    I have concerns about running IT loads with a generator with no UPS in between. IT has a pretty big leading power factor while a generator has a relatively low lagging power factor. In theory, couldn’t this trip off the generator?

  15. srtyeh on April 13, 2021 at 12:39 am

    Why can’t i pause this to take notes…..

  16. kishor bodhale on April 13, 2021 at 12:43 am

    Sir why utility power is change over to DG?

  17. robinvannoor on April 13, 2021 at 12:43 am

    Is there down time when moving load from second UPS to the static bypass?

  18. Taha Taha on April 13, 2021 at 12:47 am

    WHAT IS THE MAX ELECTRICAL POWER CAN SUPPLY FROM UPS AND CAN WE OPERATE CHILLERS 800 KVA AND IF POSSIBLE FOR HOW MANY MINUTS OR HOURS .THANKS

  19. Hannah. on April 13, 2021 at 12:48 am

    Whoever is speaking sounds like John Benjamin